Experientia Studio Build Phase 1

 
 

This is as the space was when we purchased this property in April 2007 (First 2 pics) First job is to remove all the cross beams so we can gain the addtional available height. This is a structural issue because those beams hold the roof together. So after consultation a plan to install 28 foot LVL beam under the ridge beam to hold the roof up instead. We also have to change out the eaves venting as we will be applying batt insulation directly to the roof  so we need to allow for venting directly up each rafter to a ridge vent which will be installed in phase 2.

Raise ceiling, install exterior venting

November 9, 2009